Manual Chapter :
Platform Installation
Applies To:
Show Versions
Platform Installation
About installing the VELOSCX Series platform
VELOS
CX Series
platformAfter you have reviewed the hardware requirements and become
familiar with the
VELOS
CX Series
platform, you can install
the platform into a rack. It is important that you install this platform in a
secure area, with adequate ventilation and temperature control.Due to
the weight of the platform, it is recommended that you use a lift to transport
and install the chassis. The lift handles on the chassis can support the
weight of an empty chassis, but it is recommended to only use them to maneuver
the chassis on and off of the lift. Manually lifting the chassis risks
personal injury.
Before you install this platform, review the
environmental guidelines to make sure that you are installing the platform
into a compatible rack and in the appropriate environment.
Due to the
larger size and weight of chassis platforms, F5 recommends that you install
these platforms near the bottom of the rack.
F5
strongly recommends that you install the chassis into a rack before you
install any blades. This ensures that the weight of the chassis remains
manageable as you install the chassis into a rack.
After you
install a blade, wait approximately one to two minutes before installing
another to ensure that each blade has sufficient time to boot. When the Status
LED is green, the blade is fully booted.
F5 recommends that you keep all original packaging, in
case you need to repackage and ship the platform later.
Hardware included with the
VELOSCX Series AC-powered chassis
VELOS
CX Series
AC-powered chassisThe AC-powered chassis includes all of the
hardware components listed here.
Quantity | Hardware |
---|---|
2 | AC power cables (black). Might
include multiple power cable types if product is delivered
outside of the US/Canada. |
2 | RJ45 to DB9 console port cable
(beige) |
2 | RJ45F to RJ45M rolled adapter
(beige) |
1 | Rack-mount rail kit |
1 | Electrostatic discharge (ESD) wrist
strap |
Additional equipment for installing the
VELOSCX Series AC-powered chassis
VELOS
CX Series
AC-powered chassisYou will need to provide these hardware
components when installing an AC-powered chassis.
Quantity | Hardware |
---|---|
1 | 12 AWG copper grounding wire (color
code insulation, as required) |
1 | Dual ring ground terminal lug, with
0.63 inch (1.60 cm) spaced holes for 1/4" (6mm) studs. |
1 | Wire stripping tool |
1 | Crimping tool for the ground wire
(if crimp-style lug is used) |
1 | #2 Phillips screwdriver |
Hardware included with the
VELOSCX Series DC-powered chassis
VELOS
CX Series
DC-powered chassisThe DC-powered chassis includes all of the
hardware components listed here.
Quantity | Hardware |
---|---|
4 | DC power supply connectors, standard
DC power only (part number: CON-0536) |
2 | RJ45 to DB9 console port cable
(beige) |
2 | RJ45F to RJ45M rolled adapter
(beige) |
1 | Rack-mount rail kit |
1 | Electrostatic discharge (ESD) wrist
strap |
Additional equipment for installing the
VELOSCX Series DC-powered chassis
VELOS
CX Series
DC-powered chassisYou will need to provide these hardware
components when installing a DC-powered chassis.
Quantity | Hardware |
---|---|
1 | Rack-mounted power
disconnect |
8 (minimum) | 2 AWG copper wiring leads for four
power supplies |
1 | 2 AWG copper grounding wire (color code insulation, as
required) |
1 | Dual ring ground terminal lug, with
0.63 inch (1.60 cm) spaced holes for 1/4" (6mm) studs. |
1 | Wire stripping tool |
1 | Crimping tool for the ground wire
(if crimp-style lug is used) |
1 | Screwdriver,T20 Torx drive
(preferred) or flat-head |
1 | #2 Phillips screwdriver |
Peripheral hardware recommendations
For each platform, you might need to provide
additional peripheral hardware. If you plan to remotely administer the system, it
would be helpful to have a workstation already connected to the same subnet as the
management interface.
Type of hardware | Description |
---|---|
Network hubs, switches, or
connectors to connect to the platform network
interfaces | You must provide networking devices
that are compatible with the network interface ports on the
platform. BX110 blades support 10G, 25G,
40G and 100G on the QSFP28 ports. 10G requires a breakout
cable from 40G. 25G requires a breakout cable from
100G. The system controller
management port supports 10G, 1G, and 100M. To support 25-G on
BX110 blades, you must use an IEEE compliant 25-G Ethernet
switch. |
External USB CD/DVD drive or USB
flash drive | You can use any USB-certified CD/DVD
mass storage device or a USB flash drive for installing
upgrades and for system recovery. When using a USB flash drive, verify
that the drive is fully seated in the USB
port. External CD/DVD drives must be externally powered. |
Management console or console
server | You can remotely manage the platform
by connecting to a management console or console server
through the console ports on the system controllers. The
system controllers include a built-in terminal service that
enables you to access blades using SSH. In the event that network access is
impaired or not yet configured, the serial console might
be the only way to access the unit. You should perform all
installations and upgrades using the serial console, as
these procedures require reboots, in which network
connectivity is lost temporarily. |
Management workstation that is
routable to the management port | You can use the default platform
configuration if you have a management workstation set
up. |
About installing the chassis
After you have reviewed the hardware requirements and become
familiar with the
VELOS
CX Series
platform, you can install the unit into a standard 19-inch rack, which can be
either open or enclosed.Due to
the weight of the platform, it is recommended that you use a lift to transport
and install the chassis. The lift handles on the chassis can support the
weight of an empty chassis, but it is recommended to only use them to maneuver
the chassis on and off of the lift. Manually lifting the chassis risks
personal injury.
Before you install this platform, review the
environmental guidelines to make sure that you are installing the platform
into a compatible rack and in the appropriate environment.
About installing into a four-post rack
The included rack-mount rail kits are compatible with
four-post EIA racks measuring 30 inches to 42 inches deep. The rail assemblies
use a spring action design that enables you to easily install into either
square, round untapped, or tapped mounting holes.
Detailed instructions for installing the rack-mount rail kit
are included in the kit hardware by the manufacturer.
Be sure to follow steps 5 and 6 from the
rack-mount rail kit detailed instructions to ensure that the rail assemblies
are fully secured to the rack.
An example of a chassis secured in a four-post
rack using rack manufacturer-provided screws

Rack-mount rail kit hardware
When you are installing using the rack-mount
rail kit, use these components.
Quantity | Hardware |
---|---|
1 | Fixed rail assembly (left
hand) |
1 | Fixed rail assembly (right hand) |
8 | #8-32 x .38 inch flat-head screws,
Phillips |
8 | #8-32 x .38 inch pan-head screws, Phillips |
8 | Conical washer adapter |
Install the chassis on shelf-style rail
assemblies
Before you install the chassis into a
four-post rack, verify that the rail assembles and chassis rack stop brackets
are securely installed.
You need to secure the chassis
to the rack using rack manufacturer-provided screws before you install blades. You can choose to remove the fan trays and power
supplies to make the chassis lighter for installation.
Due to
the weight of the platform, it is recommended that you use a lift to transport
and install the chassis. The lift handles on the chassis can support the
weight of an empty chassis, but it is recommended to only use them to maneuver
the chassis on and off of the lift. Manually lifting the chassis risks
personal injury.
Before you install this platform, review the
environmental guidelines to make sure that you are installing the platform
into a compatible rack and in the appropriate environment.
- Use a lift device to lift and hold the chassis in place during installation as you slide back until the rack stop brackets touch the rack.
- With the chassis held in place on the rack, install at least three rack-manufacturer provided screws to each rack stop bracket to secure the chassis into place.Torque per the rack manufacturer's specification.
About installing into a two-post rack
For installing into two-post racks, you use a two-post rack
mount shelf kit that is provided as a separate upgrade option. To order this
kit, contact F5 Support at support.f5.com and request "Field Upgrade: Two-Post
Rack Mount Kit, Shelf Style Extra Deep Chassis."
Install the chassis into a two-post rack
Before you install the chassis into a
two-post rack, verify that the two-post rack mount shelf and chassis rack stop
brackets are securely installed.
You will need these
tools to install the two-post rack and secure the chassis:
- #2 Phillips head bit and torque driver rated for at least 2.0 Newton-meters (18 inch-pounds)
You need to install the chassis before
you install blades. You can choose to remove the fan trays and power supplies
to make the chassis lighter for installation.
- Remove the rear support from the assembly by removing the six (6) flathead screws.
- Verify that you can slide the nut plate within the rear support.
- Install the rear support assembly to the rear of the rack and secure it with at least two (2) screws.The brackets are symmetrical, and you can mount either end to the rack.Use slots that are not adjacent to each other. Tighten screws to the rack manufacturer's recommended torque.You can use "tacky wax" to hold the screw to the driver while you are positioning the screw.
- Position the main assembly so that the front support is flush to the rack post.
- With the front support in position, slide the nut plate so that the nuts line up with the countersink holes.
- Use two screws to hold the main assembly in position.Use 2.0 Newton-meters (18 inch-pounds) of torque on these screws.
- Use at least two screws to secure the front support to the rack.Use slots that are not adjacent to each other. Tighten screws to the rack manufacturer's recommended torque.
- Install the remaining four flathead screws into the rear support.Use 2.0 Newton-meters (18 inch-pounds) of torque on these screws.
- Repeat steps 1-8 to install an assembly to the other side of the rack.
- Install the chassis rack stop brackets to the mid-mount position on the left and right sides of the chassis using the included hardware.Use 2.0 Newton-meters (18 inch-pounds) of torque on these screws.
- Use a lift device to lift and hold the chassis in place during installation and slide the chassis back until the chassis rack stop brackets touch the rack.
- With the chassis held in place on the rack, install three rack-manufacturer provided screws to each rack stop bracket to secure the chassis into place.Tighten screws to the rack manufacturer's recommended torque.The chassis is now secured to your two-post rack. You can now reinstall all components into the chassis, as needed.
About the front bezel with LCD touchscreen
The front bezel with LCD touchscreen on the
VELOS
chassis is detachable. You can
remove the bezel to access the power supply units (PSUs).This product is
sensitive to electrostatic discharge (ESD). F5 recommends that you use proper
ESD grounding procedures and equipment when you install or maintain the unit,
including attaching a ground strap to the ground strap receptacle location on
the front left side of the chassis.
Install the front bezel with LCD touchscreen
The front bezel
with LCD touchscreen is not pre-installed on your
VELOS
chassis, so you should install it before you can use the system. All photos shown are examples. The appearance of your
components or accessories might vary slightly.
- Pick up the front bezel using the indentations provided.
- Align the metal tab on the back left side of the replacement bezel with the corresponding cutout on the left side of the chassis, and then rotate the right hand side of the bezel toward the chassis..
- Press in on the right side until the bezel snaps into place and is secured to the chassis.Avoid pinching fingers when installing bezel.
About preventing electrostatic discharge (ESD)
damage
Damage from electrostatic discharge (ESD) can occur if you
do not use proper ESD grounding procedures and equipment when installing or
performing maintenance on chassis components. F5 provides an ESD wrist strap
with
VELOS
blades and system
controllers for you to use when installing and maintaining blades and chassis
components.Wrist strap ground location on the CX410 chassis

Connect the electrostatic discharge (ESD) wrist
strap
When installing or maintaining blades or
chassis components, be sure to use an electrostatic discharge (ESD) wrist
strap to help prevent damage to your system from ESD.
- Place the wrist strap over your wrist and tighten the strap to make sure it has good contact with your bare skin.
- Grasp the banana plug attached to the end of the strap and insert it into the wrist strap ground location on the chassis.
About grounding the chassis
You must ground the chassis after you install it in a rack.
The chassis ground lug is located on the back of the chassis.
Do not secure multiple bonding or grounding connectors with
the same bolt. The grounding connectors do not need to be removed to perform
service or installation procedures. You can connect other bonding or grounding
conductors to a grounding connector provided a reliable bond between the
connector and the equipment is not disturbed during installation, service, or
maintenance of the platform.
The AC-powered platform requires a two-hole, 1/4 inch stud hole, .63 inch hole
spacing ground lug. The tongue should be a maximum of .7 inches wide x 1.4
inches long. Minimum wire size is #12 AWG wire, though common lugs of this
size are compatible with #2 AWG (an example is Panduit part number
LCCX2-14A-E).
The DC-powered platform requires a two-hole, 1/4 inch stud hole, .63 inch hole
spacing ground lug. The tongue should be a maximum of .7 inches wide x 1.4
inches long. Minimum wire size is #2 AWG wire (an example is Panduit part
number LCCX2-14A-E).
All grounding cable terminal lugs
must meet appropriate safety standards.
The platform must be grounded to a common
bonding network (CBN).
You should coat bare
conductors with an appropriate antioxidant compound before you make crimp
connections. You should bring all unplated connectors, braided strap, and bus
bars to a bright finish and then coat them with an antioxidant before you
connect them.
Chassis ground lugs

Connect the ground lug to the ground terminal
You must provide these components to
properly ground the chassis:
- Crimping tool
- Wire stripping tool
- Dual ring ground terminal lug (such as, Panduit compression connector lug, part number: LCCX2-14A-L)
- For AC-powered chassis: one 12 AWG copper grounding wire long enough to reach from the chassis to the common bonding network (CBN)
- For DC-powered chassis: one 2 AWG copper grounding wire long enough to reach from the chassis to the common bonding network (CBN)
After the unit is installed in the
rack and before you provide power to the system, you need to connect the
grounding hardware.
- Use the wire stripping tool to remove insulation as specified by the connector's manufacturer from the end of the copper grounding wire.
- Insert the stripped end of the copper grounding wire into the open end of the ground terminal lug until the wire stops.
- Crimp the barrel of the ground terminal lug and verify that the wire is securely attached to the ground terminal.
- Remove the M6 Keps nuts from the ground lug on the back of the chassis.
- Install the ground terminal lug onto the chassis ground terminals.
- Secure the ground terminal lug with the M6 Keps nuts.Use 35 to 40 inch-pounds (4.0 TO 4.5 Newton-meters) of torque on these Keps nuts.
- Connect the ground wire to a common bonding network (CBN).
About powering the VELOSCX Series
AC-powered chassis
VELOS
CX Series
AC-powered chassisThe
VELOS
CX410 Series
AC-powered chassis ships with two power cords that you must use with the
installed power supplies to connect the chassis to site power. The base system
includes two power supplies, but the chassis supports up to four power supplies.You must apply power to the chassis
before you install or disconnect blades from the chassis.
Do not use any cords other than those
specifically designed for the
VELOS
chassis.The power supply unit (PSU) cord is used as the main
disconnect device, ensure that the socket-outlet is located or installed near
the equipment and is easily accessible.
Le cordon d'alimentation est utilisé comme interrupteur général.
La prise de courant doit être située ou installée à proximité de l'équipement
et être facile d'accès.
This unit has more than one power supply unit (PSU)
cord. Disconnect all PSU cords before servicing to avoid electric
shock.
Cet appareil comporte plus d'un cordon d'alimentation. Afin de
prévenir les chocs électriques, débrancher les deux cordons d'alimentation
avant de faire le dépannage.
Connect AC power to the chassis
You can connect the power cables to
the chassis after you install it in a rack.
- On the back of the chassis, locate the power outlets that correspond to the locations of the power supplies.Each outlet is labeled to ensure that you connect each power cord to the appropriate outlet.
- Attach the power cord to the outlet until it is firmly seated.
- Plug the power cord into an approved power source.
- Repeat this process for each power supply in the chassis.
- Verify that the LEDs on the front of the installed power supplies are lit to ensure that they are powered properly.The power supplies are located under the removable bezel on the front of the chassis.
About powering the VELOSCX Series DC-powered chassis
VELOS
CX Series
DC-powered chassisIf you ordered a DC-powered chassis, your
VELOS
CX Series
chassis comes pre-installed with DC
power supplies.Before you power this
VELOS
DC-powered platform, see Guidelines for
DC-powered equipment
and Guidelines for
NEBS platforms
.
You should coat bare
conductors with an appropriate antioxidant compound before you make crimp
connections. You should bring all unplated connectors, braided strap, and bus
bars to a bright finish and then coat them with an antioxidant before you
connect them.
Connect DC power to the chassis
You will need these tools to assemble
and wire the DC connector plug:
- Wire stripping tool
- T20 Torx driver
Be sure that the DC power source
is off and the ground lug is connected to the ground terminal before you
connect the platform to the DC power source.
After the platform is installed in
a rack, you can connect the platform to the DC power source. When you connect
the DC power source, you should also follow the safety requirements defined
for your network operations center (NOC).
Although the chassis ships with only two power
supply units (PSUs), the chassis includes four (4) terminal blocks. F5
recommends that you install all four (4) connector plugs upon initial
setup.
- Review the DC power supply label and determine the correct wire size for your installation.
- Strip approximately 0.75 inches (19 mm) of insulation off of each positive and negative wire where you connect the wire to the connector plug.Repeat for each of the four plugs.
- Use a T20 Torx driver to torque the screw to 22-40 inch-pounds (2.5-4.5 Newton-meters).Repeat for each of the four plugs.
- Connect the negative DC power lead to the -48V terminal on the connector plug.This is the terminal on the right-hand side of the plug as viewed from the rear of the chassis. It is also labeled on the chassis.
- Connect the positive DC power lead to the +48V terminal on the connector plug.This is the terminal on the left-hand side of the plug as viewed from the rear of the chassis. It is also labeled on the chassis.
- Plug the connectors into the backplane connectors and secure them by tightening the two screws on each connector.Torque to 22-40 inch-pounds (2.5-4.5 Newton-meters).
- Repeat this process for each power supply in the chassis.
- Power on the DC power source.The system should begin to boot.
- Verify that the LEDs on the front of the installed power supplies are lit to ensure that they are powered properly.The power supplies are located under the removable bezel on the front of the chassis.
Connect the cables and other hardware
After you have installed the unit
into the rack, connect the cables and other hardware.
In the event that network access is impaired or not
yet configured, the serial console might be the only way to access the
unit. You should perform all installations and upgrades using the serial
console, as these procedures require reboots, in which network
connectivity is lost temporarily.
- If you are using the default network configured on the management interface, connect an Ethernet cable to the management port on both system controllers installed in the chassis.For EMI compliance, shielded cables are required for the management port, and the shield must be grounded at both ends.
- Connect the console port to a management console or console server. Depending on which F5 system you have and the console network to which you are attaching, you can use either the supplied RJ45 to DB9 console port cable or the RJ45F to RJ45M rolled serial adapter to connect the system to a serial console.
- Connect the RJ45 to DB9 console port cable to the console port on the system.The default baud rate and serial port configuration is 19200/8-N-1.
- Connect the RJ45F to RJ45M rolled serial adapter to the console port if you are connecting the system to a serial console server with a standard CAT5 cable, and then connect the CAT5 cable to the adapter. The adapter provides the appropriate pinout connection to your equipment. For information about cable and connector pinout specifications, seeF5 Platforms: Accessoriesat techdocs.f5.com/en-us/hw-platforms/f5-plat-accessories.html.The RJ45F to RJ45M rolled serial (pass-through) adapter (CBL-0143-00)
- Connect power to installed power supplies:Be sure to route the power cords away from the fan tray so that the cords do not impede access to it.
- For AC-powered systems, connect a power cable to the power input panel on all installed power supplies, and then connect the cable to the power source.
- For DC-powered systems, attach an assembled DC terminal block to all installed power supply units and then connect the cables to your DC mains power source.
- Connect any optical transceiver modules to your blades.
- Remove the protective film from the LCD touchscreen using the small cutout on the lower right corner of the film.
You can now assign a management IP address to the
system, and then license and provision the software.
Optionally, you should run the
QKView
utility. This
utility collects configuration and diagnostic information about your
system into a single file that you can provide to F5 Technical Support to
aid in troubleshooting. For more information, see
K12878: Generating diagnostic data using the qkview utility.About installing BX110 blades in a VELOS chassis
You can install up to eight BX110 blades in a
VELOS
CX410 chassis.When you initially receive the chassis,
the slots that can contain these blades are filled with blanks. A blank must
be installed in each empty slot to ensure proper thermal management and
regulatory compliance. To add a new blade, you first remove the blank from the
corresponding slot and then insert the blade. Be sure to keep the blanks in
case you need to change the blade configuration later. You should not operate
the chassis for an extended period of time without all slots populated.
This product is
sensitive to electrostatic discharge (ESD). F5 recommends that you use proper
ESD grounding procedures and equipment when you install or maintain the unit,
including attaching a ground strap to the ground strap receptacle location on
the front left side of the chassis.
Install a blade
Check if a blank is in the slot in
which you want to install a blade. If so, you must first remove it.
You can install a blade in the
chassis without powering down the system.
- Remove the protective cap from the back of the blade.
- Carefully slide the blade into the slot.
- Before the blade is fully seated, press the blue latch release on the front of the blade to release the ejector handle.If the handle does not pop out, pull out on the blade until it does.
- Slide the blade in until the ejector contacts the catch inside the chassis.
- Press the silver ejector handle until the blade is locked in place.
- Repeat this process with each blade until all blades are secured in the unit.After you install a blade, wait approximately one to two minutes before installing another to ensure that each blade has sufficient time to boot. When the Status LED is green, the blade is fully booted.
Remove a blade blank
If a blank is installed in the slot
where you want to install a blade, you must remove it. If the slot does not
contain a blank, you can skip this procedure. F5 recommends that you store
blanks in a safe place for later use.
- Select the slot in which you want to insert a blade.
- Grasp the handle and pull toward you to remove the blade blank.
Remove a blade
You can remove a blade from the
chassis without powering down the system.
- Identify the blade that you would like to remove from the chassis.The chassis supports blade hot swap, but optionally, you can choose to halt the blade at the command line interface (CLI).
- Disconnect all cables and remove any optical modules.
- Press the blue latch release on the front of the blade to release the ejector handle.
- Grasp the ejector handle and pull toward you, ensuring that you support the weight of the blade as you remove it from the chassis.
If you are not immediately
installing a new blade into the empty slot, be sure to insert a blade blank
into the empty slot.
Blade blanks
or blades must be installed in all unused slots, as they help ensure
proper airflow within the chassis and EMI compliance of the
unit.
About system management
You can manage your
CX Series
platform by connecting to the active system
controller in your system using the floating IP address.Even if you use DHCP to configure
other management IP addresses for your system, you must manually configure the
floating IP address.
With
VELOS
platforms, you
can either manually assign or use DHCP to assign management IP addresses on a
per-system controller basis. Initially, all blades installed in the chassis
belong to a single default chassis partition, which you can access using a
partition management IP address. The partition IP address enables you to
access the system to configure other aspects of the product, such as the
VLANs, link aggregation, and so on. A blade within a cluster is also known as a slot. Each slot must
be assigned to a chassis partition, and slots are initially assigned to a default
partition.
You can manage your system using these methods:
- CLI
- webUI
- Rest API
For more information about administering and configuring your VELOS system, see
VELOS Systems: Administration and
Configuration
at support.f5.com/csp/knowledge-center/hardware. Configure management IP addresses using the CLI
After you connect your system
controllers to a management console or console server, you can configure a
floating management IP address and individual management IP addresses for the
system controllers using the command-line interface (CLI).
- Connect to a management console or console server.The default baud rate and serial port configuration is 19200/8-N-1.
- Log in using the admin account.su adminThe default login credentials are admin/admin. When logging in as admin for the first time, the system prompts you to change the password.
- Change to config mode.configThe CLI prompt changes to include(config).
- Configure the management IP address for controller-1.system mgmt-ip config [ipv4|ipv6] controller-1 address<ip_address>Example:system mgmt-ip config ipv4 controller-1 address 192.0.2.10
- Configure the management IP address for controller-2.system mgmt-ip config [ipv4|ipv6] controller-2 address<ip_address>Example:system mgmt-ip config ipv4 controller-2 address 192.0.2.11
- Configure the floating IP address for the system controllers.system mgmt-ip config [ipv4|ipv6] floating<ip_address>Example:system mgmt-ip config ipv4 floating 192.0.2.15
- Configure the default gateway, if not using DHCP.system mgmt-ip config [ipv4|ipv6] gateway<gateway_ip>Example:system mgmt-ip ipv4 gateway 192.0.2.254
- Configure the default CIDR prefix length.system mgmt-ip config [ipv4|ipv6] prefix-length<prefix_length>Example:system mgmt-ip ipv4 prefix-length 24
- Commit the configuration changes.commit
The system saves the new IP addresses and
gateway address for your system controllers. You can now use the floating IP
address that you assigned to access the system either over SSH or using the
webUI. The floating IP address will always be available on the primary system
controller.